City report · study · 1993

Options for change (1993)

Options for change : land use choices for the waterfront plan : a document for public review and comment

A study by the Port of San Francisco setting out land use options for the waterfront plan, for public review and comment.The Board adopted a resolution urging the Port Commission to keep the fishing industry on the waterfront in October 2000. Scan on the Internet Archive ↗

Cost per berth
about $50 million per berthScan 117 ↗
Pier 45 repair
$13.4 millionScan 55 ↗
Port land reserved
70%Scan 2 ↗
Piers reserved
21 piersScan 17 ↗

“[name withheld]” stands for a name the release withholds (Privacy).

Report recommendations
  • The report proposes land use options focused on primarily non-water-dependent uses for underused Port sites.Scan 2 ↗
  • The report states the objective of a flexible waterfront plan is to let the Port manage its property more effectively than in the past.Scan 33 ↗
  • The Advisory Board reached a consensus to reconsider existing waterfront policies and regulations and urge amendments if necessary.Scan 23 ↗
Board decisions
  • Port may seek and spend federal funds to repair earthquake damage on Pier 45 at Fisherman's Wharf.Record · Journal page ↗
  • 1993 · This reportPort of San Francisco
  • Lease of Pier 47 at Fisherman's Wharf for fish processing and sport fishing assigned to United Shellfish Company; finally passed.Record · Journal page ↗
  • Franciscan Restaurant's lease at Pier 43-1/2, Fisherman's Wharf, third amendment finally passed by the Board.Record · Journal page ↗
  • Lease amendment with Bundox Restaurant for the Waterfront Restaurant at Pier 7-1/2 approved, finally passed.Record · Journal page ↗
  • Resolution urging the Port Commission to keep the fishing industry on the waterfront, especially at Fisherman's Wharf, was adopted.Record · Journal page ↗
15 quotes from the scan

Printed words Quoted from the page as read from the scan.

Backgrounds-335e32a6eb23

“The Waterfront Plan is being prepared under the guidance of the Waterfront Plan Advisory Board, which will report its recommendations to the San Francisco Port Commission.”

Scan 2

Findings-e0e3151a49b1

“A closer inspection reveals that Port buildings and finger piers are underutilized and deteriorating.”

Scan 2

Findings-2f5c0635c8b3

“Alternatively, the Advisory Board determined that seven piers would not be required for water-dependent activities.”

Scan 17

Backgrounds-83a7e4b4fa2e

“Twelve years have passed since the last comprehensive planning effort was completed for the San Francisco waterfront.”

Scan 23

Backgrounds-c012b42085bf

“The California State Lands Commission has jurisdiction over the lands granted in trust to the Port of San Francisco.”

Scan 23

Findings-c9b7969ab94a

“Breakwater construction, which could alleviate this problem, is very expensive in relation to economic return from this use.”

Scan 45

Findings-2e455fa4e8ce

“The CAC has developed a draft Fisherman’s Wharf Plan that has not yet been presented to the Port Commission or Planning Commission.”

Scan 55

Findings-05d075e0494b

“Although existing terminal at Pier 35 does not operate efficiently, close proximity to Fisherman’s Wharf offers an advantage for cruise ship customers.”

Scan 77

Findings-eb4c84aad1c6

“The Port’s willingness to accept historic, and low, industrial rates of return on seawall lots developed for affordable housing in this area contributed to the transformation of the neighborhood.”

Scan 98

Findings-f9af98c67a44

“Existing regulations do not encourage fill removal -by granting credit for use elsewhere on the waterfront.”

Scan 109

Findings-dce20f820d94

“Currently, both of the Port’s container terminals are operating well below capacity.”

Scan 117

Findings-f4b240d9e5e0

“Most suffered damage during the 1989 [name withheld] earthquake and three of the buildings currently are uninhabitable.”

Scan 117

Findings-d0fbd8141c48

“Chief among these is the lack of comprehensive review of the project concept by all of the decision-making agencies early in the process.”

Scan 129

Report recommendations-e6e500a3c488

“It has also been suggested that the final plan be submitted to the voters, to ensure the necessary mandate to proceed with improvements consistent with the plan.”

Scan 129