Into the 21st century : building a new facility to continue Laguna Honda Hospital's mission

A study by the Department of Public Health weighing three options for replacing the Laguna Honda Hospital and recommending one of them.The Board affirmed the Planning Commission's certification of the final environmental impact report in August 2002. Scan on the Internet Archive ↗

Area
64 acresScan 14 ↗
Cost
$548.4 million escalated dollarsScan 8 ↗
New beds
1207 new patient bedsScan 22 ↗
Period
July 1997 to July 2003Scan 22 ↗
Report recommendations
  • The planning team unanimously endorses Alternate C as the recommended Project for this Report.Scan 64 ↗
Findings
  • The report states Alternate C is the only concept that won neighborhood acceptance.Scan 62 ↗
  • Alternate C requires the shortest construction time and causes no loss of beds during construction.Scan 64 ↗
Board decisions
  • 1992 · This reportCity and County of San Francisco, Department of Public Health
  • Resolution declares $502,515,000 (≈ $1.0 billion in 2026 dollars) in bonds necessary to replace Laguna Honda Hospital, and was adopted.Record · Journal page ↗
  • Proposed $437 million (≈ $883.8 million in 2026 dollars) plan to replace Laguna Honda HospitalRecord · Journal page ↗
  • Vote on $299 million (≈ $604.7 million in 2026 dollars) to replace Laguna Honda Hospital; first vote passed.Record · Journal page ↗
  • Up to $299M (≈ $604.7 million in 2026 dollars) to rebuild Laguna Honda nursing hospitalRecord · Journal page ↗
  • The Board affirmed the Planning Commission's certification of the Laguna Honda Hospital replacement project's final environmental impact report.Record · Journal page ↗
2 more Board decisions after the report
  • Appellants challenged the Planning Commission's certification of the Laguna Honda Hospital replacement environmental report at a public hearing.Record · Journal page ↗
  • Board tabled a motion to prepare findings disapproving the Laguna Honda Hospital replacement environmental report certification.Record · Journal page ↗
30 quotes from the scan

Printed words Quoted from the page as read from the scan.

Findings-773ba22e36c2

“It provides by far the bulk of long-term care services on which generations have depended.”

Scan 14

Findings-7a9ba3c3723a

“Because of their physical deficiencies, the facilities at Laguna Honda are operating under special waivers from State and Federal regulatory agencies.”

Scan 14

Findings-cddf9865f201

“Laguna Honda Hospital is located on a beautiful, hilly 64-acre site at the approximate center of San Francisco.”

Scan 14

Findings-eb8d175ce4c6

“The hospital’s 30-bed open ward structure is no longer permitted for reasons of infection control, patient management, and patient dignity and privacy.”

Scan 14

Findings-f0449e01d8c3

“The principal patient care buildings at Laguna Honda are between 65 and 80 years old.”

Scan 14

Report recommendations-7f369ced357a

“The total area of new construction is about 442,000 square feet.”

Scan 22

Report recommendations-7f4c403abf0e

“A new 50-unit two-bed per room Residential Care Facility is constructed on the former site of Clarendon Hall.”

Scan 22

Report recommendations-f11a70e0bd8f

“The second phase adds approximately 424,000 square feet to the new hospital, and provides 557 more patient beds.”

Scan 22

Report recommendations-199a890e2ba6

“The completed project would improve functionality and operational e:niciency.”

Scan 54

Findings-26f3c14e0a7a

“These investigations found that no other site (or sites) could duplicate the major advantages of Laguna Honda's current location.”

Scan 54

Findings-91fcc16a1934

“The City already owns the land and the Hospital is an established feature in its environment.”

Scan 54

Findings-5c191c3e65f7

“Alternate A costs $211.4 million more than Alternate C, Alternate B costs $25.6 million more.”

Scan 62

Findings-7562b27a883b

“Alternate B requires a major new service road from Clarendon Avenue that entails significant reworking and disruption of the site.”

Scan 62

Findings-7dd533612d29

“Alternate A, which maintains the form of the existing hospital, results in a very compromised functional arrangement.”

Scan 62

Findings-cb54e03b8e33

“By requiring the shortest construction time, it yields the most timely completion date.”

Scan 64

Report recommendations-6ce5f4171804

“As a replacement program, the recommended Project does not make additional demands on the City's General Fund that are associated with capital expansion programs.”

Scan 84

Report recommendations-b32b04be391b

“The Per Bed construction cost in 1992 dollars is $225,000.”

Scan 84

Report recommendations-964930a143aa

“At $759.8 million estimated project cost, Alternate A is the most expensive of the three options studied.”

Scan 102

Report recommendations-6e4b7ac574ee

“Like Alternate A, the existing Clarendon facility is also demolished and replaced by a 50-unit residential care facility.”

Scan 104

Report recommendations-c3a66e88bd79

“The total area of new construction would be about 837,000 gross square feet, plus a 32,000 square foot residential care facility.”

Scan 104

Report recommendations-6312512ed5eb

“Alternate C, however, would be completed 1 1/2 years sooner, in July 2003.”

Scan 106

Report recommendations-bf56d282934e

“Based on the preliminary project schedule noted above, Alternate B is estimated to cost approximately $574.0 million.”

Scan 106

Report recommendations-6afa3208c90b

“557 beds would be built in Phase 2, beginning July 1, 2000, at $358.94 per square foot (escalated construction cost).”

Scan 134

Backgrounds-71b32c0799c6

“Four patients per room is the maximum number allowed by the Federal Health Care Financing Administration (HCFA) if an institution is to receive Medi-Cal and Medicare reimbursement.”

Scan 134

Backgrounds-9a46dd25e55e

“The Laguna Honda Hospital space program is currently based on typical nursing units of seven 4-bed patient rooms and two single patient rooms per unit.”

Scan 134

Report recommendations-bc2883232f4c

“650 beds would be built in Phase 1, beginning July 1, 1997, at $291.99 per square foot (escalated construction cost).”

Scan 134

Findings-a1d5015def40

“Employee benefits were computed at 27.34 percent of salaries and wages.”

Scan 152

Report recommendations-b6d3013223e9

“Medicare reimbursement rates were assumed to increase at an annual inflation rate of 3.5 percent.”