Report recommendations-1c16fb2ba9b9
“The estimated cost to implement Alternative A would be $79 million.”
Scan 11Records › City reports › Transit terminal study (1993)
Transit terminal study
A study by the Planning Department comparing transit terminal alternatives, recommending a new terminal at Main/Beale over upgrading the existing Transbay Terminal.In February 2001 the Board adopted, as amended, a resolution to form a joint powers agency for a new Transbay Terminal transit facility. Scan on the Internet Archive ↗
Printed words Quoted from the page as read from the scan.
Report recommendations-1c16fb2ba9b9
“The estimated cost to implement Alternative A would be $79 million.”
Scan 11Report recommendations-27a1655c9b65
“The estimated cost to implement Alternative B would be $101 million.”
Scan 11Report recommendations-8d25a0ac7f0d
“The estimated cost to implement Alternative X would be $93 million.”
Scan 11
Scan 11Backgrounds-6825f260ade4
“The Transbay Transit Terminal (Terminal) and its adjoining ramp system were completed in 1939 as part of the construction of the Bay Bridge.”
Scan 12Findings-f276bc2bf31d
“Currently there are 12 commute, non-commute and tour bus operators using the Terminal building.”
Scan 12
Scan 20Findings-528b9cd20361
“The OSA study released in 1992 concluded that the Terminal building needed substantial upgrades to meet current seismic and other fire/life/safety codes.”
Scan 20Backgrounds-8ab1d1ce6515
“The Terminal Separator provided an elevated connection between I-80 and the Embarcadero Freeway prior to being damaged by the earthquake.”
Scan 20Report recommendations-aab849c7c39b
“Based on projections in the Transit Needs Study, AC Transit would require forty bus berths on the third floor deck.”
Scan 26Report recommendations-02cdef62feda
“Alternative X would foreclose the possibility of direct Caltrain or other rail service into the Terminal.”
Scan 29Report recommendations-8029ce2aa981
“An extension of Caltrain and/or high speed rail could be accommodated in a separate underground rail station located underneath Howard Street and private property between Natoma and Howard Streets.”
Scan 29Report recommendations-c4a6232e6be5
“Alternative X would basically retain the existing Terminal building facade and create additional space for buses by reconfiguring the existing bus deck.”
Scan 29Report recommendations-2d6d5d0967a6
“Alternative A, with a new transit terminal and other land uses stacked above, may be a complicated construction project and would require approximately thirty months.”
Scan 58Report recommendations-c5e2efcab349
“Alternative B is estimated to take twenty-six months to complete construction.”
Scan 58Report recommendations-ed35cf8f43e1
“Alternative X, which would require major modifications to the existing Terminal, is estimated to take twenty-six months for construction.”
Scan 58
Scan 72Report recommendations-ce3ab1f9967a
“This terminal will have a total of 7 bus platforms and 44 bus bays.”
Scan 72Report recommendations-0f0ce96a03dd
“This terminal will have a total of 5 bus platforms and 40 bus bays.”
Scan 76
Scan 77Report recommendations-d42570660105
“The new terminal will have twice as many bus bays as the existing terminal.”
Scan 81Report recommendations-e0ad718b2fac
“Underground parking garage could be constructed on the southeast section of the block bounded by First, Howard, Second, and Mission Streets.”
Scan 81Findings-dafef76e16bd
“Notes to Alternative B: We have not included any costs for historic preservation impacts.”
Scan 109Findings-e99f6d07501a
“No costs are included for interim bus operations which would have to be relocated during construction.”
Scan 109Identifier ia:C124914494