“not to build any new above-ground ramps north of Fell Street to replace the demolished sections of the Central Freeway.”
Scan 0Records › City reports › Central freeway retrofit plan cost analysis (1997)
Central freeway retrofit plan cost analysis
A cost analysis by the Board of Supervisors Budget Analyst comparing options to retrofit or replace the damaged Central Freeway, and their funding. Scan on the Internet Archive ↗
“[name withheld]” stands for a name the release withholds (Privacy).
Printed words Quoted from the page as read from the scan.
Board decision citedPrinted words, misread in placess-a839e4cccecb
“not to build any new above-ground ramps north of Fell Street to replace the demolished sections of the Central Freeway.”
Scan 0Findings-b53537ab0ec6
“On October 17, 1989, the [name withheld] Earthquake caused extensive damage to the Central Freeway.”
Scan 0Findings-86af9c49d2ac
“Caltrans demolished the upper deck of the Central Freeway from Mission to Oak Streets.”
Scan 1Report recommendations-f17c7f696c53
“This alternative would retrofit the existing lower deck from South Van Ness Avenue to Page Street and widen the lower deck to a four-lane single deck configuration.”
Scan 1Backgrounds-e53e2de12bb6
“Senate Bill 181 (SB181), approved in 1991, prohibits Caltrans from proceeding with the repair or replacement of the Central Freeway until the Board of Supervisors approves one of the selected alternatives.”
Scan 2Findings-09049d62e3b4
“Mr. [name withheld] reports that all of the construction funds would need to be identified before Caltrans would begin the reconstruction of the Central Freeway.”
Scan 3Report recommendations-cb7502b4b94f
“Alternative 8/9B is the least expensive of the four Alternatives, at an estimated construction cost of $38.5 million and a total estimated cost of $49.45 million.”
Scan 3Report recommendations-e3960a19ad8a
“As reflected above, Alternative 1B is the most expensive of the four above-noted Alternatives, at an estimated construction cost of $52 million and a total estimated cost of $67.6 million.”
Scan 3Board decision citedPrinted words, misread in placess-c0173b2e34e0
“Resolution 541-92, approved by the Board of Supervisors in 1992 which made it a City policy to not build any new above-ground freeway ramps north of Fell Street”
Scan 7Findings-61b80693f403
“As a result, Mr. [name withheld] reports that neither ER nor SHOPP funds would be available to be used for capital projects identified from the Proposition H plan.”
Scan 8
Scan 8Findings-d0b74e13eb45
“City-wide assessed property values increased by 16.4 percent between 1991 and 1996.”
Scan 9Report recommendations-9f53dbd71257
“Alternative 1B, which is the Proposition H Alternative, is the most expensive of the four Alternatives, at an estimated construction cost of $52 million and a total estimated cost of $67.6 million.”
Scan 10Report recommendations-13e99877c14b
“Alternative 8/9B is the least expensive of the four Alternatives, at an estimated construction cost of $38.5 million and a total cost of $49.45 million.”
Scan 11Findings-953a755c9582
“Of the original $40,000,000 of Federal Emergency Relief (ER) funds specifically allocated for the Central Freeway, approximately $17,500,000 currently remains.”
Scan 11Report recommendations-e6aa97a58acb
“This plan is estimated to cost approximately $200,000, if the City were to contract for such services.”
Scan 11Identifier ia:C124914731