Findings-add0b40ab210
“Residents of Chinatown perceive reduced connectivity resulting from the removal of Embarcadero Freeway following the 1989 earthquake.”
Scan 63Records › City reports › Draft environmental impact statement/draft environmental impact… (1…
Draft environmental impact statement/draft environmental impact report for the Third Street light rail project in the City and County of San Francisco
A draft environmental impact report by the San Francisco Planning Department assessing the proposed Third Street light rail project and its alternatives.The Board passed an ordinance allowing advertising on E-Line and Third Street Light Rail boarding platforms in November 2006. Scan on the Internet Archive ↗
“[name withheld]” stands for a name the release withholds (Privacy).
Printed words Quoted from the page as read from the scan.
Findings-add0b40ab210
“Residents of Chinatown perceive reduced connectivity resulting from the removal of Embarcadero Freeway following the 1989 earthquake.”
Scan 63Report recommendations-f69866c1b7ff
“Identified the Western Pacific site as the preferred location, pending negotiations with the Port.”
Scan 80Backgrounds-fc77513a53dc
“For capital cost and phasing reasons, the PTC selected the Market Street Subway alignment as the initial phase and the Central Subway as the ultimate project.”
Scan 80Findings-fb66f8be42d3
“MUNI operates 79 bus lines seven days a week and, on an annual basis, carries over 211 million riders.”
Scan 152
Scan 213Findings-26c6ebf8ec59
“Thickness of the sand in the study area along Third Street are approximately 30 meters (98 feet).”
Scan 280Findings-c067ceb29e97
“The northbound Third Street tunnel and surface alignment is within surficial deposits to approximately Townsend Street.”
Scan 280Backgrounds-1b94b0fe79cb
“The study area is underlain by four groundwater basins as defined by the U. [name withheld].”
Scan 289Report recommendations-c6add42cd833
“The operation of the New Central Subway would generate approximately 80 additional jobs beyond that of the IOS, including at the maintenance facility.”
Scan 345Findings-81c0e7250fc8
“The Western Pacific site is underlain by heterogeneous artificial fill to depths ranging from 1.8 meters (6 feet) to 13 meters (43 feet) below the ground surface.”
Scan 378Findings-3eae2be9ed56
“Groundwater levels in the study area have been reported to range between 1.8 meters (6 feet) bgs and 8.5 meters (28 feet) bgs.”
Scan 394Report recommendations-a42bec221160
“Construction of the Light Rail Alternative would require excavation below the groundwater level along portions of the alignment.”
Scan 394
Scan 394Backgrounds-d21b9531c876
“Measures to avoid adverse effects caused by the presence of hazardous materials during construction are required by Article 20 of the San Francisco Municipal Code.”
Scan 394Findings-7cffa8ca687d
“Overall, the Light Rail Alternative would result in a net reduction in regional emissions, although a slight increase in regional emissions would result from the Maintenance Facility.”
Scan 412Report recommendations-f1728bb0c6a1
“The construction-related impacts would be reduced to a less than significant level if the construction mitigation measures for the No Build/TSM Alternative, described above, were implemented.”
Scan 412Findings-42d6d44afc41
“An estimated $203 million will be spent on maintaining MUNI's infrastructure through FY 2006.”
Scan 447Backgrounds-5513c96a3b33
“Because fare levels are policy determinations by the Board of Supervisors, this Financial Condition report assumes fare levels will remain at current rates.”
Scan 447
Scan 447
Scan 447Backgrounds-6d9deee701b9
“Policy 4.1: Rapid transit lines from all outlying corridors should lead to stations and terminals that are adjacent or connected to each other in downtown San Francisco.”
Scan 485Identifier ia:C124915258