City report · staff report · 1996

Review of the projected costs and economic benefits associated with… (1996)

Review of the projected costs and economic benefits associated with the San Francisco Giants' proposed ballpark at China Basin

A review by the Board of Supervisors' Budget Analyst of the projected costs and economic benefits of a proposed privately financed downtown ballpark at China Basin.The Board allowed the Giants ballpark at China Basin in March 1996, a decision that followed the Budget Analyst's report. Scan on the Internet Archive ↗

Construction
$255 millionScan 2 ↗
Toxic cleanup
$5.0 million to $20 million or moreScan 5 ↗
Port site
13.5 acre siteScan 15 ↗
Possessory interest tax
$3.5 million annuallyScan 25 ↗
Findings
  • Toxic remediation of the 13.5 acre site is the single largest potential cost factor for the ballpark.Scan 15 ↗
  • The Budget Analyst estimates General Fund costs of up to $300,000 (≈ $644,245 in 2026 dollars) annually for the ballpark.Scan 3 ↗
  • The Port of San Francisco could face the greatest financial risk, or possible gain, under the Giants proposal.Scan 3 ↗
Board decisions
  • 1996 · This reportCity and County of San Francisco, Board of Supervisors, Budget Analyst
  • Budget Analyst ordered to report on city costs of the proposed China Basin ballpark before the March 26, 1996 vote.Record · Journal page ↗
  • Hearing on the benefits and costs of the proposed China Basin Ballpark was referred to the Joint Budget and Government Efficiency Committee.Record · Journal page ↗
  • Motion asking the Budget Analyst to report on benefits of the proposed China Basin Ballpark was referred to the Board for February 12, 1996.Record · Journal page ↗
  • The Board directed the Budget Analyst to report on city benefits of the proposed China Basin ballpark, with top priority.Record · Journal page ↗
  • Giants ballpark allowed at China Basin; it opened in 2000Record · Journal page ↗
20 quotes from the scan

Printed words Quoted from the page as read from the scan.

Backgrounds-1c0052646acd

“On January 8, 1996, the Board of Supervisors adopted a motion directing the Budget Analyst to analyze any and all costs of the Giants’ ballpark proposal.”

Scan 2

Report recommendations-95e1263f7f2f

“Total construction project costs for the ballpark are estimated at $255 million.”

Scan 2

Backgrounds-f2bbf8eda80e

“The San Francisco Giants (Giants) proposed Proposition B as the first step toward construction of a privately financed downtown ballpark.”

Scan 2

Findings-5150d9b12484

“The Port must acquire or lease a 155,000 square foot parcel of land from Caltrans which is to be included in the ground lease for the ballpark site.”

Scan 3

Findings-705852514b22

“The net cost of this level of service would approximate $800,000 annually, or $300,000 annually more than the net cost of service to Candlestick Park.”

Scan 5

Findings-989d2b476e99

“The Authority’s report included no specific costs for the potential capital improvements.”

Scan 12

Findings-0b8ebb8708a1

“Potential costs for encapsulation versus an environmental cleanup requiring significant offsite disposal of toxics, have been presented as approximately $5.0 million for encapsulation, to as much as $20 million or more for a full cleanup.”

Scan 15

Findings-0c606f8a8286

“The Port does not anticipate significant expenditures for relocating the ten tenants.”

Scan 15

Findings-1cdbb8018496

“The Port’s maintenance facility currently occupies 135,000 square feet at Pier 46B.”

Scan 15

Findings-806a78cbc219

“The single largest potential cost factor connected to the use of the 13.5 acre site for a new ballpark will be the need for toxic remediation of the site.”

Scan 15

Backgrounds-88348b0633a8

“The Budget Analyst’s report on the 1989 China Basin Ballpark Proposal included an estimate of up to $11.0 million for the acquisition of the Caltrans property.”

Scan 15

Findings-c122ba607d9a

“In 1989, the Budget Analyst was informed that such estimated demolition costs ranged from approximately $2.0 million to $7.0 million in order to demolish the four structures on and near to Pier 46B.”

Scan 15

Findings-ff49ae3d5c3b

“The Budget Analyst has learned that the encapsulation strategy is viewed as a viable alternative by engineering and environmental health professionals.”

Scan 16

Findings-e31201d78035

“The loss of the Giants as a Candlestick Park tenant beginning with the year 2000 baseball season would mean decreased lease revenue to the Recreation and Park Department of between $1.0 and $1.2 million annually.”

Scan 20

Report recommendations-aaef7ee8d809

“The San Francisco Redevelopment Agency will be asked to debt finance, using Tax Increment Bonds, a $10 million contribution to the project.”

Scan 24

Backgrounds-ba2bbcebf4a8

“State law mandates that 20% of project area appropriations must be set aside as a contribution to housing programs.”

Scan 24

Findings-4e4eeae4c68d

“No cost estimates have been provided by Authority for the identified capital projects.”

Scan 26

Findings-5c7b171591b8

“The Budget Analyst has not verified the source data or the accuracy of computations in the updated report on economic impacts.”