Management audit of the San Francisco Municipal Railway (1996)

Management audit of the San Francisco Municipal Railway

An audit by the Budget Analyst of the San Francisco Municipal Railway's management, staffing, revenue, facilities and contracting practices. Scan on the Internet Archive ↗

Staff
approximately 3,570 employeesScan 60 ↗
Operating budget
approximately $280 millionScan 4 ↗
On schedule
62 percent of vehiclesScan 108 ↗
Fare revenue
$91 million annually, $72 million cashScan 185 ↗
Findings
  • The study team found that only 62 percent of MUNI vehicles adhere to their published schedules, against a Department goal of 85 percent.Scan 108 ↗
Report recommendations
  • The report recommends that the Department and the Commission consider alternative organizational structures to increase management accountability.Scan 82 ↗
  • The audit recommends a report on contracting options be given to the Commission within three months after acceptance of the audit.Scan 274 ↗
Board decisions
  • Ordinance proposed to appropriate $125,000 (≈ $268,435 in 2026 dollars) for a Budget Analyst management audit of the Municipal Railway; referred to Budget Committee.Record · Journal page ↗
  • Ordinance appropriating $125,000 (≈ $268,435 in 2026 dollars) for a management audit of the Municipal Railway was finally passed.Record · Journal page ↗
  • 1996 · This reportCity and County of San Francisco, Board of Supervisors, Budget Analyst
  • Supervisors Hsieh and Alioto requested a hearing on the July 1996 Muni management audit, referred to the Budget Committee.Record · Journal page ↗
  • Ordinance appropriating $358,789 (≈ $753,211 in 2026 dollars) for thirty-seven Municipal Railway positions to implement Prop J audit recommendations passed for second reading.Record · Journal page ↗
  • Board finally passed $358,789 (≈ $753,211 in 2026 dollars) for 37 new Municipal Railway positions to carry out Prop J audit recommendations.Record · Journal page ↗
  • Board finally passed an amendment to the 1996-97 salary ordinance creating thirty-seven Municipal Railway positions.Record · Journal page ↗
  • Municipal Railway may accept about $107.1M (≈ $224.8 million in 2026 dollars) in federal grants and local matching funds for ten capital projects.Record · Journal page ↗
1 more Board decisions after the report
  • Municipal Railway awarded Electric Transit Incorporated a contract up to $168,752,888 (≈ $354.3 million in 2026 dollars) for articulated and standard trolley coaches.Record · Journal page ↗
32 quotes from the scan

Printed words Quoted from the page as read from the scan.

Findings-1f4144c44b94

“20 new diesel engines were purchased over two years ago, but never installed.”

Scan 24

Report recommendations-af83fda1ce9b

“We have recommended an additional three parts storekeeping positions so that storerooms are open between 6 AM and 7 PM on weekdays, and between 8 AM and 5 PM on weekends.”

Scan 24

Backgrounds-870a43c8a471

“Other large transit properties with multiple vehicle modes are organized according to general service.”

Scan 82

Findings-65f06d6327d0

“Currently, two of the Assistant Chief Inspector positions are vacant, due to assignment of those two staff persons to Transportation Superintendent duties.”

Scan 108

Findings-ba8eabbdf412

“The Transit Service Supervision Unit is authorized a total of 71 positions, including one Chief Inspector, five Assistant Inspectors, two clerical support positions, and 64 inspectors.”

Scan 108

Findings-fa4ec8b07485

“The number of budgeted fixed post and mobile transit supervisor positions has steadily decreased from a high of 95 in FY 1981-82 to 64 in FY 1995-96.”

Scan 108

Findings-22859aed57b9

“During the last six months, there have been an average of 1,800 road calls per month.”

Scan 134

Report recommendations-3a30bb6b4d01

“A conservative estimate of a 10 percent reduction of such calls due to the implementation of an effective quality assurance program would reduce the calls by 180.”

Scan 134

Report recommendations-5ac53f2894b7

“Such a program should be reinstated and implemented by maintenance managers based on a more careful review of available road call data.”

Scan 134

Report recommendations-6396815ee9f2

“We recommend that three additional employees, as identified below, who are currently working in other MUNI divisions be restored immediately to the Maintenance Division.”

Scan 160

Findings-1fddcd8e16d6

“General procedures manuals for the Municipal Railway’s Revenue Division, including the Collection, Reconciliation, and Processing Units, have not been updated in the last 10 years.”

Scan 185

Findings-493aebef9d7a

“Of the $91 million in annual fare revenue, 79 percent, or approximately $72 million of fare revenues are collected from cash fares.”

Scan 185

Findings-73ea83f0ff9c

“A review of the current use of these facilities and properties indicate that none are presently considered surplus to the Municipal Railway.”

Scan 200

Backgrounds-8fe9b8d0878f

“Proposition J requires that the Budget Analyst examine MUNI’s potential for selling surplus assets.”

Scan 200

Findings-2c6216214935

“MUNI's fleet replacements will use more than half of the $1.34 billion in capital project funding that is projected in the CIP from 1995 through 2005.”

Scan 204

Report recommendations-bcd65e16db2c

“Such an analysis is needed to lay the groundwork for a Facilities Master Plan.”

Scan 204

Findings-ce6f661c4d7e

“The MTC, which allocates most federal funds for transit capital projects, ranks facilities projects low.”

Scan 204

Report recommendations-25b5aae14fb5

“The SRTP includes a long range (i.e. post 2005) plan to relocate the Kirkland Division to the Islais Creek site.”

Scan 213

Findings-aaa3417e6e5e

“The Kirkland site is located on a full block of approximately 2.6 acres in the Fisherman’s Wharf area.”

Scan 213

Findings-416d483e4bb9

“MUNT is currently leasing the ground rights to a portion of the substation located at 79 Stevenson Street, which is being used as a cafe by the tenants.”

Scan 217

Findings-90e1ee26ac82

“The terms of the lease provide the City with rental revenues of $3.41 per square foot per month.”

Scan 217

Findings-277323b0fa88

“Discussions with Maintenance Division managers indicate that since 1989 there have been no dedicated and knowledgeable staff assigned to a warranty tracking and reimbursement program.”

Scan 239

Findings-7e37bce84754

“Clearly, there should have been a much greater return on warranty claims over the last six years--at least to the level achieved in previous years.”

Scan 239

Report recommendations-17df934ee173

“Add miscellaneous production and design costs estimated at approximately $42,600.”

Scan 265

Report recommendations-63d7f15d566e

“The Department included an increase in its printing budget of $63,000 in FY 1995-96 to $132,000 in FY 1996-97.”

Scan 265

Backgrounds-3434fc674e84

“Section 6.1 of the Public Transportation Department’s Short-Range Transit Plan (SRTP) cites two resolutions, Numbers 86-0103 and 87-0327, which were approved by the Public Utilities Commission (PUC).”

Scan 273

Findings-d338581dff54

“Available literature on contracting for transportation services is vast, but is also inconclusive about the advantages of using contract rather than publicly-owned services.”

Scan 273

Report recommendations-1550682ec4f5

“Therefore, the Public Transportation Commission should direct MUNI management to identify service elements, and develop and present criteria that will encourage practical, cost effective contracting solutions for transit services.”

Scan 274

Findings-22fa46dcb9cb

“Appendix 7.1.1 to this audit report is a side letter agreement between the San Francisco Municipal Railway and the Transport Workers Union Local 250A concerning “Privatization” which, according to the City Attorney’s Office, is still in effect.”

Scan 274

Findings-3e0895041d50

“However, these SRTP interim policy guidelines are not comprehensive and do not establish an environment that is conducive to contracting.”

Scan 274

Report recommendations-5cdefaeb8e70

“A report which clearly presents options available to the City should be provided to the Commission no later than three months after the acceptance of this management audit.”

Scan 274

Findings-d030896ee78b

“In response to the first directive contained in PUC Resolution No. 87-0327, MUNI developed Appendix E of the SRTP entitled “Procedures for Handling Unsolicited Proposals and any Resulting Complaints.””

Scan 274