20 Board decisions about Brode Iron Works, in date order. Each links to its printed page.
- Supervisor Bancroft reported that Brode Iron Works held the steel contract for the John Swett School, finding no general contract. linked by the name only, not checked
- Public Works recommended sixty more days for Brode Iron Works to finish steel work at Spring Valley Grammar School.
- Three contractors were granted extensions of time to finish work at the Hall of Justice and Spring Valley Grammar School. linked by the name only, not checked
- Three contractors were granted extensions of time on Hall of Justice and Spring Valley school building contracts, passed for printing. linked by the name only, not checked
- Payments to Henry C. Fitts and Brode Iron Works for Peabody and Spring Valley Grammar school work were passed for printing. linked by the name only, not checked
- A resolution proposed paying five contractors and suppliers a total of $13,122.10 for work on several San Francisco schools.
- Payments made for school desks and building work
- Brode Iron Works and Foster & Vogt were granted extensions of time on their city construction contracts. linked by the name only, not checked
- Brode Iron Works and Foster & Vogt were granted extensions of time on their city construction contracts, including the John Swett School steel.
- Brode Iron Works and the Ferrolite Company were granted extra time to finish city school and jail construction contracts. linked by the name only, not checked
- Brode Iron Works was granted a ninety-day extension to finish its steel contract on the John Swett School Building. linked by the name only, not checked
- Resolution to pay $8,950 for work at John Swett Grammar School was passed for printing.
- Payments of $705 and $10,500 from the school construction account passed for printing for Franklin and John Swett schools work.
- Brode Iron Works was granted ninety more days to finish steel work on the John Swett School Building.
- Payments of $705 and $10,500 approved from the School Construction Account to Central Electric Co. and Brode Iron Works for school work. linked by the name only, not checked
- Board passed $11,205 in school construction payments to Central Electric Co. and Brode Iron Works for Franklin and John Swett schools. linked by the name only, not checked
- Board adopted $7,633.25 in progress payments to three contractors building the Jean Parker, John Swett and Harrison schools. linked by the name only, not checked
- School construction payments proposed, including $4,074.75 to Finlayson-Stettin for Jean Parker School; vote continues.
- Public Works recommends a ninety-day extension for Brode Iron Works to finish steel work on John Swett School. linked by the name only, not checked
- Payments totalling $8,950 to Brode Iron Works and O. C. Holt for John Swett Grammar School work passed.