  • Supervisor Bancroft reported that Brode Iron Works held the steel contract for the John Swett School, finding no general contract. linked by the name only, not checked
    1910outcome not readJournal 1910, p. 1067 ↗
  • Public Works recommended sixty more days for Brode Iron Works to finish steel work at Spring Valley Grammar School.
  • Three contractors were granted extensions of time to finish work at the Hall of Justice and Spring Valley Grammar School. linked by the name only, not checked
    1 Sep 1910passedJournal 1910, p. 965 ↗
  • Three contractors were granted extensions of time on Hall of Justice and Spring Valley school building contracts, passed for printing. linked by the name only, not checked
    26 Sep 1910passed first readingJournal 1910, p. 949 ↗
  • Payments to Henry C. Fitts and Brode Iron Works for Peabody and Spring Valley Grammar school work were passed for printing. linked by the name only, not checked
    28 Nov 1910passed first readingJournal 1910, p. 1149 ↗
  • A resolution proposed paying five contractors and suppliers a total of $13,122.10 for work on several San Francisco schools.
    12 Dec 1910outcome not readJournal 1910, p. 1193 ↗
  • Payments made for school desks and building work
    19 Dec 1910passedJournal 1910, p. 1209 ↗
  • Brode Iron Works and Foster & Vogt were granted extensions of time on their city construction contracts. linked by the name only, not checked
  • Brode Iron Works and Foster & Vogt were granted extensions of time on their city construction contracts, including the John Swett School steel.
  • Brode Iron Works and the Ferrolite Company were granted extra time to finish city school and jail construction contracts. linked by the name only, not checked
  • Brode Iron Works was granted a ninety-day extension to finish its steel contract on the John Swett School Building. linked by the name only, not checked
  • Resolution to pay $8,950 for work at John Swett Grammar School was passed for printing.
    1911passed first readingJournal 1911 ↗
  • Payments of $705 and $10,500 from the school construction account passed for printing for Franklin and John Swett schools work.
    1911passed first readingJournal 1911 ↗
  • Brode Iron Works was granted ninety more days to finish steel work on the John Swett School Building.
  • Payments of $705 and $10,500 approved from the School Construction Account to Central Electric Co. and Brode Iron Works for school work. linked by the name only, not checked
    1911outcome not readJournal 1911 ↗
  • Board passed $11,205 in school construction payments to Central Electric Co. and Brode Iron Works for Franklin and John Swett schools. linked by the name only, not checked
    6 Feb 1911passedJournal 1911 ↗
  • Board adopted $7,633.25 in progress payments to three contractors building the Jean Parker, John Swett and Harrison schools. linked by the name only, not checked
    3 Apr 1911passedJournal 1911 ↗
  • School construction payments proposed, including $4,074.75 to Finlayson-Stettin for Jean Parker School; vote continues.
    3 Apr 1911outcome not readJournal 1911 ↗
  • Public Works recommends a ninety-day extension for Brode Iron Works to finish steel work on John Swett School. linked by the name only, not checked
    5 Sep 1911referredJournal 1911 ↗
  • Payments totalling $8,950 to Brode Iron Works and O. C. Holt for John Swett Grammar School work passed.
    27 Nov 1911passedJournal 1911 ↗