Organisation · organisation
Brode Iron Works
An organisation in 20 Board decisions, 1910–1911.
20Board decisions about it
1910–1911first and last decision
In short
- 1 Sep 1910Three contractors were granted extensions of time to finish work at the Hall of Justice and Spring Valley Grammar School. linked by the name only, not checked
- 1911Brode Iron Works and Foster & Vogt were granted extensions of time on their city construction contracts, including the John Swett School steel.
Who appears together
Lines show who appears in the same decisions. It doesn't mean they made a deal.
People
- Charles A. Nelsonproposed 3 · 1911
- John L. Hergetproposed 1 · 1911
Organisations
- Central Electric Companynamed in 3
- Lange & Bergstromnamed in 2
- Caldwell & Companynamed in 2
Places
- Division Stnamed in 1
More from the records
Who was paid · 7 organisations
| Central Electric Company | 3 decisions |
| Lange & Bergstrom | 2 decisions |
| Whitaker and Ray Wiggin Company | 2 decisions |
| Finlayson Stettin Company | 2 decisions |
| Knowles & Kaiser | 2 decisions |
| Contra Costa Construction Company | 1 decision |
How many decisions pay each one; amounts are not shown until a person checks them.
Votes · 8 roll calls
yes 124no 0absent 0
8 printed roll calls; 8 were unanimous.
Decisions, by type
| resolution | 11 |
| contract | 6 |
| other | 2 |
| claim | 1 |
Decisions, by outcome
| passed | 10 |
| passed first reading | 4 |
| referred | 2 |
4 decisions have no outcome read yet.
All 20 decisions · in date order
- Supervisor Bancroft reported that Brode Iron Works held the steel contract for the John Swett School, finding no general contract. linked by the name only, not checked
- Public Works recommended sixty more days for Brode Iron Works to finish steel work at Spring Valley Grammar School.
- Three contractors were granted extensions of time to finish work at the Hall of Justice and Spring Valley Grammar School. linked by the name only, not checked
- Three contractors were granted extensions of time on Hall of Justice and Spring Valley school building contracts, passed for printing. linked by the name only, not checked
- Payments to Henry C. Fitts and Brode Iron Works for Peabody and Spring Valley Grammar school work were passed for printing. linked by the name only, not checked
- A resolution proposed paying five contractors and suppliers a total of $13,122.10 for work on several San Francisco schools.
- Payments made for school desks and building work
- Brode Iron Works and Foster & Vogt were granted extensions of time on their city construction contracts. linked by the name only, not checked
- Brode Iron Works and Foster & Vogt were granted extensions of time on their city construction contracts, including the John Swett School steel.
- Brode Iron Works and the Ferrolite Company were granted extra time to finish city school and jail construction contracts. linked by the name only, not checked
- Brode Iron Works was granted a ninety-day extension to finish its steel contract on the John Swett School Building. linked by the name only, not checked
- Resolution to pay $8,950 for work at John Swett Grammar School was passed for printing.