Organisation · organisation
United States Cast Iron Pipe and Foundry Company
An organisation in 49 Board decisions, 1909–1925.
49Board decisions about it
1909–1925first and last decision
In short
- 25 Oct 1909Resolution authorizing school construction payments for Mission Grammar, South End and Madison schools was taken up; outcome continues next page. linked by the name only, not checked
- 24 Jan 1910Payments from the Fire Protection Account approved for pipe, fittings and fire cistern construction at several San Francisco intersections.
- 10 Mar 1924Board deferred the submarine pipe contract award to a New Jersey firm, asking committees to investigate and withhold funds.
Who appears together
Lines show who appears in the same decisions. It doesn't mean they made a deal.
People
- Ralph McLeranproposed 7 · 1924–25
- Thomas Jenningsproposed 7 · 1909–14
- John A. Kellyproposed 2 · 1910
Organisations
- Standard Oil Companynamed in 11
- Southern Pacific Companynamed in 10
- Old Mission Portland Cement Companynamed in 9
Places
- Baker Stnamed in 3
- Seventeenth Stnamed in 3
- Sloat Blvdnamed in 3
Left out: San Francisco Chronicle, paid to print the Board's legal notices, not a party.
More from the records
Who was paid · 77 organisations
| Standard Oil Company | 11 decisions |
| Southern Pacific Company | 10 decisions |
| Old Mission Portland Cement Company | 9 decisions |
| Pacific Gas and Electric Company | 8 decisions |
| Atchison, Topeka and Santa Fe Railway Company | 8 decisions |
| Spring Valley Water Company | 7 decisions |
How many decisions pay each one; amounts are not shown until a person checks them.
Votes · 22 roll calls
yes 349no 0absent 18
22 printed roll calls; 22 were unanimous.
Decisions, by type
| resolution | 49 |
Decisions, by outcome
| passed | 15 |
| passed first reading | 14 |
20 decisions have no outcome read yet.
All 49 decisions · in date order
- Payments totalling $101,273.25 for the auxiliary fire protection water system, including pipe and fireboat contracts, passed for printing. linked by the name only, not checked
- Payments totaling $101,273.25 made for fire-protection water pipe, freight and fireboat construction. linked by the name only, not checked
- Payments of $91,295.54 to US Cast Iron Pipe and $3,589.70 to Southern Pacific for fire water pipe were passed for printing.
- Payments totalling $94,885.24 to pipe supplier and Southern Pacific for the fire-protection auxiliary water system were finally passed.
- Resolution authorizing school construction payments for Mission Grammar, South End and Madison schools was taken up; outcome continues next page. linked by the name only, not checked
- Passed final payment of $84,767.22 for auxiliary fire water system pipe and its freight charges. linked by the name only, not checked
- Payments totalling $84,767.22 for auxiliary fire-water pipe and its railroad freight were passed for printing.
- A payment for sundry supplies and services for the Board of Public Works, including Union Oil Co. asphaltum, was proposed.
- Payments totalling $88,161.74 for pipe and freight on the auxiliary fire water supply system were passed for printing.
- Board authorized $88,161.74 in payments for pipe and freight for the Auxiliary Water System for fire protection.
- Payments totalling $63,723.69 for pipe and freight for the fire-protection water system passed for printing. linked by the name only, not checked
- Board approved payments of about $94,805 for fire cisterns and pipe for the Auxiliary Water Supply System.
Pages that mention it
Printed pages of the decisions on this page.
Journal 1909
Journal 1910
Journal 1913
Journal 1924