  • Payments totalling $101,273.25 for the auxiliary fire protection water system, including pipe and fireboat contracts, passed for printing. linked by the name only, not checked
    13 Sep 1909passed first readingJournal 1909, p. 829 ↗
  • Payments totaling $101,273.25 made for fire-protection water pipe, freight and fireboat construction. linked by the name only, not checked
    20 Sep 1909passedJournal 1909, p. 842 ↗
  • Payments of $91,295.54 to US Cast Iron Pipe and $3,589.70 to Southern Pacific for fire water pipe were passed for printing.
    11 Oct 1909passed first readingJournal 1909, p. 927 ↗
  • Payments totalling $94,885.24 to pipe supplier and Southern Pacific for the fire-protection auxiliary water system were finally passed.
    25 Oct 1909passedJournal 1909, p. 955 ↗
  • Resolution authorizing school construction payments for Mission Grammar, South End and Madison schools was taken up; outcome continues next page. linked by the name only, not checked
    25 Oct 1909outcome not readJournal 1909, p. 955 ↗
  • Passed final payment of $84,767.22 for auxiliary fire water system pipe and its freight charges. linked by the name only, not checked
    15 Nov 1909passedJournal 1909, p. 1017 ↗
  • Payments totalling $84,767.22 for auxiliary fire-water pipe and its railroad freight were passed for printing.
    29 Nov 1909passed first readingJournal 1909, p. 1011 ↗
  • A payment for sundry supplies and services for the Board of Public Works, including Union Oil Co. asphaltum, was proposed.
    13 Dec 1909outcome not readJournal 1909, p. 1165 ↗
  • Payments totalling $88,161.74 for pipe and freight on the auxiliary fire water supply system were passed for printing.
    13 Dec 1909passed first readingJournal 1909, p. 1165 ↗
  • Board authorized $88,161.74 in payments for pipe and freight for the Auxiliary Water System for fire protection.
    20 Dec 1909passedJournal 1909, p. 1173 ↗
  • Payments totalling $63,723.69 for pipe and freight for the fire-protection water system passed for printing. linked by the name only, not checked
    1910passed first readingJournal 1910, p. 306 ↗
  • Board approved payments of about $94,805 for fire cisterns and pipe for the Auxiliary Water Supply System.
    24 Jan 1910passedJournal 1910, p. 103 ↗
  • Payments from the Fire Protection Account approved for pipe, fittings and fire cistern construction at several San Francisco intersections.
    24 Jan 1910passedJournal 1910, p. 102 ↗
  • Payments totaling $94,805.80 to pipe and cistern contractors for fire protection were passed for printing. linked by the name only, not checked
    8 Feb 1910passed first readingJournal 1910, p. 84 ↗
  • Payments for pipe and steel specials for the auxiliary fire water system were proposed; the vote continues on the next page.
    14 Feb 1910outcome not readJournal 1910, p. 188 ↗
  • Board adopted payments for pipe, steel specials and freight for the Auxiliary Water System for fire protection.
    21 Feb 1910passedJournal 1910, p. 201 ↗
  • Extends by sixty days the time for the United States Cast-iron Pipe and Foundry Company to supply Auxiliary Water System pipe.
    9 Mar 1910passedJournal 1910, p. 254 ↗
  • Extension of sixty days granted to the United States Cast-iron Pipe and Foundry Company to supply pipe for the Auxiliary Water Supply System.
    15 Mar 1910passedJournal 1910, p. 275 ↗
  • Proposed payments for pipe, freight and cast steel for an auxiliary fire protection water system. linked by the name only, not checked
    28 Mar 1910outcome not readJournal 1910, p. 317 ↗
  • Proposed payments to four suppliers for Auxiliary Water Supply System pipe, valves and freight, from the Fire Protection Account. linked by the name only, not checked
    13 Jun 1910passed first readingJournal 1910, p. 608 ↗
  • Board approved $15,290.55 in Fire Protection Account payments for Auxiliary Water Supply System pipe, valves and freight. linked by the name only, not checked
    20 Jun 1910passedJournal 1910, p. 615 ↗
  • Payment of $210,000 was approved to United States Cast Iron Pipe and Foundry Company for auxiliary fire-protection water pipe.
    31 Oct 1910passedJournal 1910, p. 1052 ↗
  • $12,000 set aside to restore surveys in the Excelsior and Mission
    14 Jul 1913outcome not readJournal 1913, p. 747 ↗
  • Final passage of Resolution 10288 authorizing city payments to contractors, suppliers and claimants from bond and general funds.
    21 Jul 1913passedJournal 1913, p. 760 ↗
  • The Board passed for printing a resolution authorizing payments to contractors for sewers, schools, a hospital, streets and supplies.
    6 Oct 1913passed first readingJournal 1913, p. 974 ↗
  • Resolution proposed to authorize payments from city funds to 23 contractors, suppliers and officials, listed in the text.
    1914outcome not readJournal 1914, p. 1347 ↗
  • The Board authorizes payments from city funds to many contractors and suppliers, including Hetch Hetchy road work and hospital supplies. linked by the name only, not checked
    7 Dec 1914outcome not readJournal 1914, p. 1384 ↗
  • Clinton Fireproofing Co. paid $23,822.45 for the Seventeenth Street car barn
    8 Mar 1915outcome not readJournal 1915, p. 312 ↗
  • Clinton Fireproofing Co. paid $23,822.45 for the Seventeenth Street car barn linked by the name only, not checked
    15 Mar 1915outcome not readJournal 1915, p. 330 ↗
  • Board deferred the submarine pipe contract award to a New Jersey firm, asking committees to investigate and withhold funds.
    10 Mar 1924passedJournal 1924, p. 269 ↗
  • Board adopted Resolution 22517 repealing the cancellation of the $196,802 Hetch Hetchy pipe contract with a foundry company.
    2 Jun 1924passedJournal 1924, p. 666 ↗
  • Board considered $200,000 from the Water Construction Fund for submarine pipe for the Hetch Hetchy Aqueduct, with contract to a foundry. linked by the name only, not checked
    2 Jun 1924outcome not readJournal 1924, p. 666 ↗
  • $200,000 approved for submarine cast iron pipe for the Hetch Hetchy Aqueduct, awarded to United States Cast Iron Pipe and Foundry Company.
    16 Jun 1924passedJournal 1924, p. 679 ↗
  • Grant Smith & Company paid $49,309.60 for the Pulgas Tunnel linked by the name only, not checked
    4 Aug 1924outcome not readJournal 1924 ↗
  • Resolution authorizing payments to 32 claimants, including Spring Valley Water Company and Pacific Coast Steel, passed for printing. linked by the name only, not checked
    25 Aug 1924passed first readingJournal 1924, p. 988 ↗
  • Resolution authorizes payments to suppliers and contractors, mainly for Hetch Hetchy water construction, from the Water Construction Fund. linked by the name only, not checked
    15 Sep 1924outcome not readJournal 1924, p. 1041 ↗
  • Supervisor McLeran's resolution authorizes payments from water and Municipal Railway funds to cement, oil, insurance and utility suppliers; passed for printing.
    22 Sep 1924passed first readingJournal 1924, p. 1128 ↗
  • Payments from water and Municipal Railway funds to cement, oil, lumber and power suppliers were put forward for final passage.
    29 Sep 1924outcome not readJournal 1924, p. 1154 ↗
  • Resolution authorizing a long list of city payments to vendors and contractors from various funds, outcome continues on the next page.
    24 Nov 1924outcome not readJournal 1924, p. 1390 ↗
  • A resolution authorizes payment of dozens of city claims from departmental funds, including schools, fire, police, transit and parks bills. linked by the name only, not checked
    22 Dec 1924outcome not readJournal 1924, p. 1517 ↗
  • Twenty payments from city funds were proposed for Hetch Hetchy water works, supplies, legal and engineering work, and a Lincoln Park boulevard job. linked by the name only, not checked
    26 Jan 1925passed first readingJournal 1925, p. 123 ↗
  • The Board moves to authorize Hetch Hetchy water construction fund payments to Del Monte Meat Co., M. M. O'Shaughnessy, Robert M. Searls and others. linked by the name only, not checked
    2 Feb 1925outcome not readJournal 1925, p. 152 ↗
  • Payments authorized from city funds to suppliers, contractors and pension system for library, water and Municipal Railway work; vote continues next page. linked by the name only, not checked
    24 Feb 1925outcome not readJournal 1925, p. 234 ↗
  • Resolution proposed authorizing dozens of city payments to contractors, suppliers and charities, passed for printing. linked by the name only, not checked
    16 Mar 1925passed first readingJournal 1925, p. 341 ↗
  • $800 paid to Paul Russo to settle a Municipal Railway claim
    23 Mar 1925passed first readingJournal 1925, p. 372 ↗
  • $800 paid to Paul Russo to settle a Municipal Railway claim linked by the name only, not checked
    30 Mar 1925outcome not readJournal 1925, p. 400 ↗
  • Board authorized about $119,243.32 in payments to contractors and claimants for school, Muni and Hetch Hetchy work. linked by the name only, not checked
    13 Apr 1925outcome not readJournal 1925, p. 480 ↗
  • Resolution authorizing payments on many city claims, including Cabrillo School, Hetch Hetchy pipe and park work, was passed for printing. linked by the name only, not checked
    31 Aug 1925passed first readingJournal 1925, p. 1250 ↗
  • Resolution authorizes payments to named claimants from listed city funds; amounts are not shown on this page. linked by the name only, not checked
    8 Sep 1925outcome not readJournal 1925, p. 1279 ↗