  • Willett & Burr's temporary railroad track for the Beale Street regrade, passed for printing. linked by the name only, not checked
    1911passed first readingJournal 1911 ↗
  • Willett and Burr were granted a 120-day permit to blast while grading Beale street between Folsom and Bryant streets. linked by the name only, not checked
  • Board granted Willett & Burr three hundred forty days to run a temporary railroad track on Beale Street.
  • Willett & Burr's blasting bond on Beale street between Folsom and Bryant was proposed at $10,000.
    13 Mar 1911outcome not readJournal 1911 ↗
  • Board of Public Works recommends a ninety-day extension for Willett & Burr to finish Beale Street work. linked by the name only, not checked
    2 Jan 1912referredJournal 1912 ↗
  • Willett & Burr get ninety more days on Beale Street linked by the name only, not checked
    29 Jan 1912passedJournal 1912, p. 88 ↗
  • Willett & Burr allowed to blast at the H. Levi Building
    5 Feb 1912outcome not readJournal 1912, p. 109 ↗
  • Willett & Burr allowed to blast at the H. Levi Building
    13 Feb 1912outcome not readJournal 1912, p. 119 ↗
  • A resolution to deny Willett and Burr more time on the Beale Street bridge was referred to the Streets Committee.
    9 Dec 1912referredJournal 1912, p. 1125 ↗
  • Willett & Burr granted sixty more days to finish the Beale Street re-grade contract.
    13 Jan 1913passedJournal 1913, p. 45 ↗
  • Sixteen payments from city funds were authorized to claimants and contractors for hospital, Hetch Hetchy, transit, and Fire Department work.
    4 Feb 1918passed first readingJournal 1918, p. 108 ↗
  • Willett & Burr were approved for $1,536.30 for renting motor trucks used on the Eleanor Dam, Hetch Hetchy. linked by the name only, not checked
    25 Mar 1918passedJournal 1918, p. 247 ↗
  • Fifteen payments to contractors and suppliers, including Hetch Hetchy water and Municipal Railway work, were passed for printing on McLeran's motion.
    22 Apr 1918passed first readingJournal 1918, p. 324 ↗
  • Board passed twenty-two payment claims to contractors, railways, oil firms and others for 1916-18 city work.
    29 Apr 1918passedJournal 1918, p. 335 ↗
  • Board authorized dozens of payments to contractors and suppliers for schools, Hetch Hetchy, parks and fire services, passed for printing.
    26 Jul 1920passed first readingJournal 1920, p. 633 ↗
  • Anderson & Ringrose paid $12,888 for building the Excelsior School
    2 Aug 1920outcome not readJournal 1920 ↗
  • Hetch Hetchy water-fund payments totalling about $15,000 were authorized for fuel, equipment, insurance and supplies to named suppliers.
    23 Aug 1920passed first readingJournal 1920, p. 687 ↗