Duboce Tunnel
A project in 55 Board decisions, 1922–1934.
55Board decisions about it
1922–1934first and last decision
In short
- 31 Oct 1922The Board heard protests against the proposed Duboce Tunnel, which runs beneath Buena Vista Park, on October 31, 1922.
- 29 Jun 1925Board corrected a 1922 clerical error in its minutes on the proposed Duboce Tunnel project.
- 26 Apr 1926Board adopted a resolution finding land easements on Clayton and Frederick streets needed for the Duboce Tunnel, and ordered condemnation proceedings.
- 8 Aug 1927Youdall Construction Company granted a 90-day extension to finish the Duboce Tunnel under Buena Vista Park.
- 29 Jan 1934Gallagher's motion asks the Mayor to explain a conference on Duboce Tunnel tax refunds, and the motion carried.
Who appears together
Lines show who appears in the same decisions. It doesn't mean they made a deal.
People
- Adolph Uhlproposed 2 · 1934
- William S. Scottproposed 2 · 1922
- Andrew J. Gallagherproposed 1 · 1934
Organisations
- Title Insurance and Guaranty Companynamed in 1
- Youdall Construction Companynamed in 1
- F. E. Hesthal Companynamed in 1
Places
- Frederick Stnamed in 21
- Clayton Stnamed in 18
- Carl Stnamed in 7
More from the records
Votes · 31 roll calls
yes 468no 0absent 81
31 printed roll calls; 31 were unanimous.
Decisions, by type
| resolution | 38 |
| hearing | 7 |
| motion | 3 |
| contract | 2 |
| ordinance | 2 |
| other | 1 |
Decisions, by outcome
| passed | 19 |
| continued | 5 |
| referred | 2 |
| passed first reading | 1 |
28 decisions have no outcome read yet.
All 55 decisions · in date order
- A $1,500 appropriation for test borings for the Duboce Tunnel was proposed, to be repaid through assessment.
- Resolution approved $1,500 from the General Fund for test borings for the proposed Duboce Tunnel.
- The Board heard protests against the proposed Duboce Tunnel, which runs beneath Buena Vista Park, on October 31, 1922.
- Protestants opposed the proposed Duboce Tunnel into the Sunset District at a continued Board hearing; no decision is printed yet.
- Hearing on protests against the proposed Duboce Tunnel into the Sunset District was continued to December 18, 1922.
- Protestants against the proposed Duboce Tunnel were heard, and the hearing was continued to January 4, 1923.
- Hearing on protests against the proposed Duboce Tunnel was continued to January 4, 1923.
- Protests against the Duboce Tunnel assessment district were heard and the hearing continued to next Monday at 3 p.m.
- Hearing on protests against the proposed Duboce Tunnel was continued to February 13, 1923.
- The Board continued the proposed construction of the Duboce Tunnel until October 7, 1924.
- Theodore J. Savage was retained as special counsel for the City in the Duboce Tunnel litigation for $2,500 fees.
- Board corrected a 1922 clerical error in its minutes on the proposed Duboce Tunnel project.