Project

North Point Main Sewer

A project in 33 Board decisions, 1909–1912.

33Board decisions about it
1909–1912first and last decision

In short

  • 19 Sep 1910
    Healy-Tibbitts Construction Company was granted permission to blast for the North Point Main Sewer along Sansome Street, adopted.
  • 27 Feb 1911
    C. J. Harney granted a sixty-day extension to finish North Point Main Sewer contract work, delayed by water mains.
  • 27 May 1912
    Board annulled the 1911 North Point Main Sewer contract with James F. Van Loben Sels and forfeited his bond.

Who appears together

PeopleOrganisationsPlacesJohn P. McLaughlinproposed 3Allan Pollokproposed 1John A. Kellyproposed 1Healy TibbittsConstruction Companynamed in 3Keystone ConstructionCompanynamed in 3Federal ConstructionCompanynamed in 2North Point MainSewernamed in 7North Point Stnamed in 6Sansome Stnamed in 2North Point Main Sewer

Lines show who appears in the same decisions. It doesn't mean they made a deal.

People

Organisations

Places

  • North Point Main Sewernamed in 7
  • North Point Stnamed in 6
  • Sansome Stnamed in 2

More from the records

Who was paid · 3 organisations
Healy Tibbitts Construction Company1 decision
Keystone Construction Company2 decisions
Robert C. Storrie & Company1 decision

How many decisions pay each one; amounts are not shown until a person checks them.

Votes · 15 roll calls
yes 238no 0absent 0

15 printed roll calls; 15 were unanimous.

Decisions, by type
resolution22
ordinance10
other1
Decisions, by outcome
passed17
passed first reading9
referred1

6 decisions have no outcome read yet.

All 33 decisions · in date order
  • Ordinance ordering sewer construction in Section L of the North Point Main Sewer, estimated at $47,000, passed for printing.
    2 Aug 1909passed first readingJournal 1909, p. 771 ↗
  • Payment of $10,013.25 from the Sewer Construction Account to C. J. Harney for North Point Main Sewer sections was adopted.
    9 May 1910passedJournal 1910, p. 471 ↗
  • An ordinance ordering a $165,000 sewer construction in Section A of the North Point Main Sewer was passed for printing.
    9 May 1910passed first readingJournal 1910, p. 469 ↗
  • An ordinance proposed to build Section A of the North Point Main Sewer, estimated at $165,000 from sewer bonds.
    16 May 1910outcome not readJournal 1910, p. 485 ↗
  • Board approved $13,013.25 to C. J. Harney for second installment of North Point Main Sewer work.
    16 May 1910passedJournal 1910, p. 480 ↗
  • Ordinance for sewer construction in Section C of the North Point Main Sewer, costing $105,000, passed for printing.
    2 Sep 1910passed first readingJournal 1910, p. 831 ↗
  • Healy-Tibbitts Construction Company was granted permission to blast for the North Point Main Sewer along Sansome Street, adopted.
    19 Sep 1910passedJournal 1910, p. 931 ↗
  • Healy-Tibbitts Construction Company was granted revocable permission to blast for the North Point Main Sewer along Sansome Street.
    26 Sep 1910passedJournal 1910, p. 946 ↗
  • Flinn & Treacy given 90 more days on Stockton Street
    31 Oct 1910passedJournal 1910, p. 1078 ↗
  • A payment of $31,547.52 to C. J. Harney for North Point Main Sewer work was passed for printing.
    1911passed first readingJournal 1911 ↗
  • Bill 1802 proposes building sewers in Section D 2 of the North Point Main Sewer at an estimated $80,000 cost.
    1911passed first readingJournal 1911 ↗
  • Resolution passed for printing to pay sewer contractors progress payments, including $8,935.91 to Healy-Tibbitts for the North Point Main Sewer.
    1911passed first readingJournal 1911 ↗