All decisions
33 Board decisions about North Point Main Sewer, in date order. Each links to its printed page.
- Ordinance ordering sewer construction in Section L of the North Point Main Sewer, estimated at $47,000, passed for printing.
- Payment of $10,013.25 from the Sewer Construction Account to C. J. Harney for North Point Main Sewer sections was adopted.
- An ordinance ordering a $165,000 sewer construction in Section A of the North Point Main Sewer was passed for printing.
- An ordinance proposed to build Section A of the North Point Main Sewer, estimated at $165,000 from sewer bonds.
- Board approved $13,013.25 to C. J. Harney for second installment of North Point Main Sewer work.
- Ordinance for sewer construction in Section C of the North Point Main Sewer, costing $105,000, passed for printing.
- Healy-Tibbitts Construction Company was granted permission to blast for the North Point Main Sewer along Sansome Street, adopted.
- Healy-Tibbitts Construction Company was granted revocable permission to blast for the North Point Main Sewer along Sansome Street.
- Flinn & Treacy given 90 more days on Stockton Street
- A payment of $31,547.52 to C. J. Harney for North Point Main Sewer work was passed for printing.
- Bill 1802 proposes building sewers in Section D 2 of the North Point Main Sewer at an estimated $80,000 cost.
- Resolution passed for printing to pay sewer contractors progress payments, including $8,935.91 to Healy-Tibbitts for the North Point Main Sewer.
- An extra $15,000 is proposed for building Section D-2 of the North Point Main Sewer.
- An extra $8,000 is proposed for building Section D-3 of the North Point Main Sewer.
- Keystone Construction Co. was to receive $5,478.45 as a sixth installment on the North Point Main Sewer contract.
- Resolution proposed to pay Federal Construction Co. $1,525.93 for North Point Main Sewer work.
- Construction of sewers in Section D 2 of the North Point Main Sewer was ordered at an estimated cost of $80,000.
- A sixty-day extension for C. J. Harney to finish North Point Main Sewer work was passed for printing.
- An extra $14,000 is proposed for building Section D-1 of the North Point Main Sewer.
- City paid Keystone Construction Co. $5,478.45 for a sixth installment on North Point Main Sewer work.
- C. J. Harney granted a sixty-day extension to finish North Point Main Sewer contract work, delayed by water mains.
- Payment of $802.53 to C. J. Harney for a tenth installment on North Point Main Sewer construction.
- Federal Construction Co., assigned to Metropolis Construction Co., was paid $1,525.93 for Section F of the North Point Main Sewer.
- Public Works recommended $80,000 for sewer construction in Section 15 of the North Point Main Sewer.
- Board authorized $31,547.52 in sewer fund payments to C. J. Harney for North Point Main Sewer work.
- Bill proposed ordering sewer construction in Section D-3 of the North Point Main Sewer, costing $85,000, passed for printing.
- The Board ordered construction of sewers in Section D-3 of the North Point Main Sewer, estimated at $85,000.
- An extra $15,000 appropriated for construction of Section D-2 of the North Point Main Sewer by the Board of Public Works.
- An extra $8,000 appropriated for construction of Section D-3 of the North Point Main Sewer by the Board of Public Works.
- Board of Public Works ordered to build Section E of the North Point Main Sewer, estimated at $140,000 from the sewer account.
- An extra $14,000 appropriated for construction of Section D-1 of the North Point Main Sewer by the Board of Public Works.
- Board annulled the 1911 North Point Main Sewer contract with James F. Van Loben Sels and forfeited his bond.
- John Daniel was granted 45 more days to finish North Point Main Sewer work on Treat avenue; the resolution passed to printing.