Named in the records1951–2005

164 records of San Francisco tie this place, 1951–2005: 26 decisions of the Board of Supervisors and 138 facts read from city reports. Open the full list, with filters for years, kind and outcome.

Kind
Named in the records
Records
164: 26 Board decisions, 138 facts from city reports
Years
1951–2005

What the records say

The 60 most telling of its 164 records, in date order: the ones an editor picked first, then the highest scored. The one-line summaries were written by a language model from the printed page; open the page to check the wording.

WhenWhat the record saysOutcomeSource
1951-09-04The city approved paying $806.40 (≈ $10,450 in 2026 dollars) to settle the State Harbor Commissioners' claim for damage to Pier 35 by a fireboat.passedBoard decision
scanned page ↗
1970-05-18Supervisors asked Matson Navigation Company to explain its sewage-dumping rules for ships docked at Pier 35.motionBoard decision
scanned page ↗
1970-05-18Supervisors Feinstein and Mendelsohn asked Matson Navigation Company about ship sewage dumping at Pier 35, and the Clerk was directed to comply.motionBoard decision
scanned page ↗
1974Pier 35 · use: passenger ship terminal, approximately 90 passenger ships and 60,000 passengerssiteCity report: Final environmental impact report on special area plan for the San Francisco waterfront
scanned page ↗
1975Pier 35 passenger terminal · proposes: renovation of Pier 35 as a modern passenger terminalprojectCity report: Final environmental impact report on special area plan for the San Francisco waterfront
scanned page ↗
1976Pier 35 · proposes: Renovate Pier 35 as a modern, functional passenger terminal with associated commercial recreation usesrecommendationCity report: The plan for the northeastern waterfront : a part of the Master plan of the City and County of San Francisco and a revision of the existing Northern waterfront plan : a proposal for citizen review
scanned page ↗
1978Pier 35 · other: Port Commission indicated Pier 35 is now available for developmenteventCity report: Final environmental impact report on Northpoint Pier : storage building and service yard, San Francisco
scanned page ↗
1978Northpoint Pier storage building and service yard · alternative: Use of Pier 35alternativeCity report: Final environmental impact report on Northpoint Pier : storage building and service yard, San Francisco
scanned page ↗
1978Northpoint Pier service building and service yard · proposes: service building and service yardprojectCity report: Final environmental impact report on Northpoint Pier : storage building and service yard, San Francisco
scanned page ↗
1978Service building · stories: three-story structurebuildingCity report: Final environmental impact report on Northpoint Pier : storage building and service yard, San Francisco
scanned page ↗
1978Service building · floor area sqft: approximately 7,000 square feetbuildingCity report: Final environmental impact report on Northpoint Pier : storage building and service yard, San Francisco
scanned page ↗
1978Northpoint Pier storage building · height ft: increase architectural profile of Pier 35 approximately 120 feetbuildingCity report: Final environmental impact report on Northpoint Pier : storage building and service yard, San Francisco
scanned page ↗
1978Embarcadero park extension · other: Extension of Pier 39 park along The Embarcadero to Pier 35 as mitigationmeasureCity report: Final environmental impact report on Northpoint Pier : storage building and service yard, San Francisco
scanned page ↗
1978Northpoint Pier storage building · finding: Fence and service building would be a visual and physical obstacle to the BayfindingCity report: Final environmental impact report on Northpoint Pier : storage building and service yard, San Francisco
scanned page ↗
1978Move Service Building Next to Pier 35 · alternative: Move service building next to Pier 35; increases Bay views from The EmbarcaderoalternativeCity report: Final environmental impact report on Northpoint Pier : storage building and service yard, San Francisco
scanned page ↗
1978Other Inland Location · alternative: Inland site would be further from Pier 39 complex; would allow park extension near Pier 35alternativeCity report: Final environmental impact report on Northpoint Pier : storage building and service yard, San Francisco
scanned page ↗
1978Northpoint Pier storage building · other: Ships on the west side of Pier 35 would not be visible from The EmbarcaderofindingCity report: Final environmental impact report on Northpoint Pier : storage building and service yard, San Francisco
scanned page ↗
1978Pier 35 facade addition · other: Neo-classical building extending Pier 35 facade would interfere with Pier 85 plans and lock in form for 60 yearsfindingCity report: Final environmental impact report on Northpoint Pier : storage building and service yard, San Francisco
scanned page ↗
1978Northpoint Pier Maintenance Building and Service Yard · other: storage building on Pier 35-Pier 37 bulkhead could be made compatible with Pier 35 facadeprojectCity report: Final environmental impact report on Northpoint Pier : storage building and service yard, San Francisco
scanned page ↗
1978Passageway between service building and Pier 35 · finding: EIR should discuss potential problems of litter accumulation, wind and public safety in the passagewayfindingCity report: Final environmental impact report on Northpoint Pier : storage building and service yard, San Francisco
scanned page ↗
1978Storage building · floor area sqft: 20,000 sq ft storage areabuildingCity report: Final environmental impact report on Northpoint Pier : storage building and service yard, San Francisco
scanned page ↗
1978Pier 35 · floor area sqft: about 200,000 sq ft pier areasiteCity report: Final environmental impact report on Northpoint Pier : storage building and service yard, San Francisco
scanned page ↗
1978Cruise ships on west side of Pier 35 · finding: ships on west side of Pier 35 would not be visible from The Embarcadero due to the pier's anglefindingCity report: Final environmental impact report on Northpoint Pier : storage building and service yard, San Francisco
scanned page ↗
1978City's Waterfront Plan · other: objective to retain existing maritime and maritime-related activities, particularly at Pier 35measureCity report: Final environmental impact report on Northpoint Pier : storage building and service yard, San Francisco
scanned page ↗
1978Northpoint Pier developer · other: developer expects to leave Pier 35 and to get location approval from BCDCeventCity report: Final environmental impact report on Northpoint Pier : storage building and service yard, San Francisco
scanned page ↗
1978Northpoint Pier storage building · proposes: 7,000-square-foot maintenance building on 50 pilesmeasureCity report: Final environmental impact report on Northpoint Pier : storage building and service yard, San Francisco
scanned page ↗
1978Northpoint Pier service yard · proposes: service yard proposed to be constructed near Pier 35projectCity report: Final environmental impact report on Northpoint Pier : storage building and service yard, San Francisco
scanned page ↗
1978Northpoint Pier storage building and service yard · alternative: use of Pier 35 for the proposed work, questioned by Commissioner EastmanalternativeCity report: Final environmental impact report on Northpoint Pier : storage building and service yard, San Francisco
scanned page ↗
1978Pier 35 · other: Special Area Plan designates Pier 35 for retention as a passenger terminalmeasureCity report: Final environmental impact report on Northpoint Pier : storage building and service yard, San Francisco
scanned page ↗
1981-06-22Passed for second reading, a $1.41M (≈ $5.2 million in 2026 dollars) Port Commission capital budget to remodel the passenger terminal at Pier 35.passed first readingBoard decision
scanned page ↗
1981-06-29The Port Commission's $1,413,332 (≈ $5.2 million in 2026 dollars) capital budget to remodel the passenger terminal at Pier 35 was finally passed.passedBoard decision
scanned page ↗
1983-05-16Janitorial work at the Ferry Building, Pier 35 and Fisherman's Wharf Pavilion approved for private contracting at lower cost.passedBoard decision
scanned page ↗
1983-05-16Resolution adopted finding janitorial services at the Ferry Building, Pier 35 and Fisherman's Wharf can be done cheaper privately.passedBoard decision
scanned page ↗
1984Pier 35 area map label · other: Pier Qs (under construction)siteCity report: Proposal to Pacific Fleet Battleship Homeporting Team
scanned page ↗
1985North Point Park · proposes: Provide and maintain shoreline park with generous planting, sitting and fishing areas and open water vistasmeasureCity report: Recreation and open space element of the master plan : proposal for citizen review
scanned page ↗
1986Passenger vessels at Pier 35 · other: 46,540 tons of breakbulk discharged (mainly baggage) in 1986findingCity report: Port of San Francisco economic impact report
scanned page ↗
1986Passenger vessels at Pier 35 · other: 48,746 tons of breakbulk loaded (mixture of baggage and stores) in 1986findingCity report: Port of San Francisco economic impact report
scanned page ↗
1987-11-30Port Commission ordinance proposed to fund $100,000 (≈ $296,602 in 2026 dollars) handicap access at Ferry Building and Pier 35; passed first reading.passed first readingBoard decision
scanned page ↗
1987Pier 35 dredging · other: approximately 200,000 cubic yards dredged between 1987 and 1990measureCity report: [Public information documents relating to Port of San Francisco waterfront plan project]
scanned page ↗
1987Pier 35 dredging · cost usd: between $100,000 and $150,000 per yearmeasureCity report: [Public information documents relating to Port of San Francisco waterfront plan project]
scanned page ↗
1988Pier 35 baggage and stores handling · other: Longshore work is created in handling baggage and stores at Pier 35findingCity report: Port of San Francisco economic impact report
scanned page ↗
1990Pier 35 cruise terminal · finding: fair condition, with some deterioration of the pilingsfindingCity report: [Public information documents relating to Port of San Francisco waterfront plan project]
scanned page ↗
1990Pier 35 cruise terminal · finding: narrow pier width limits circulation, approximately 200 feetfindingCity report: [Public information documents relating to Port of San Francisco waterfront plan project]
scanned page ↗
1990Pier 35 cruise terminal · finding: passenger and vehicular circulation cannot be separated due to narrow bulkhead entrancefindingCity report: [Public information documents relating to Port of San Francisco waterfront plan project]
scanned page ↗
1990Pier 35 cruise terminal · finding: no clearly delineated passenger drop-off or queuing area for buses, taxis and automobilesfindingCity report: [Public information documents relating to Port of San Francisco waterfront plan project]
scanned page ↗
1990Pier 35 cruise terminal · finding: no direct vehicular access from the street to the ship servicing area on the pier apronfindingCity report: [Public information documents relating to Port of San Francisco waterfront plan project]
scanned page ↗
1992Pier 35 · use: cruise ship terminal, available during off-season months or between cruise ship callssiteCity report: [Public information documents relating to Port of San Francisco waterfront plan project]
scanned page ↗
1992Pier 35 cruise terminal · other: two berthsbuildingCity report: [Public information documents relating to Port of San Francisco waterfront plan project]
scanned page ↗
1992Pier 35 cruise terminal · finding: need for frequent dredging and inefficient ship and passenger servicing facilitiesfindingCity report: [Public information documents relating to Port of San Francisco waterfront plan project]
scanned page ↗
1992Pier 35 cruise terminal · finding: lack of adequate parkingfindingCity report: [Public information documents relating to Port of San Francisco waterfront plan project]
scanned page ↗
1992Pier 35 cruise terminal · finding: lack of a public viewing areafindingCity report: [Public information documents relating to Port of San Francisco waterfront plan project]
scanned page ↗
1992Pier 35 cruise terminal · finding: limitations most acute when two ships call simultaneouslyfindingCity report: [Public information documents relating to Port of San Francisco waterfront plan project]
scanned page ↗
2004Port's $980,349 (≈ $1.7 million in 2026 dollars) fund balance appropriation for Pier 35 security upgrades at the cruise terminal passed first reading.passed first readingBoard decision
scanned page ↗
2004Mayor proposed appropriating $998,349 (≈ $1.8 million in 2026 dollars) in Port fund balance for Pier 35 cruise terminal security upgrades; sent to Finance Committee.referredBoard decision
scanned page ↗
2004-12-08The Mayor's ordinance to spend $998,349 (≈ $1.8 million in 2026 dollars) of Port fund balance on Pier 35 cruise terminal security was sent to committee.referredBoard decision
scanned page ↗
2005-01-04Ordinance releasing $980,349 (≈ $1.7 million in 2026 dollars) Port fund balance to pay the second phase of the Pier 35 security upgrade, passed as final.passedBoard decision
scanned page ↗
2005-01-04Ordinance passed to appropriate $980,349 (≈ $1.7 million in 2026 dollars) from Port fund balance for Pier 35 cruise terminal security upgrades.passedBoard decision
scanned page ↗
2005-01-04Port spends $980,349 (≈ $1.7 million in 2026 dollars) on Pier 35 cruise terminal security.passedBoard decision
scanned page ↗
1990Philip Williams & Associates Ltd. · other: office at Pier 35, The Embarcadero, San Francisco CA 94133agencyCity report: Status and trends report on dredging and waterway modification in the San Francisco Estuary
scanned page ↗
1982Pier 35 passenger terminal · event: new passenger terminal officially openedeventCity report: San Francisco : the mayor's annual "state of the city" report
scanned page ↗

All 164 records, with filters · this place's data as JSON · release v0.7.1 · CC0 1.0