Southeast Plant
Named in the records1956–2026
79 records of San Francisco tie this place, 1956–2026: 51 decisions of the Board of Supervisors and 28 facts read from city reports. Open the full list, with filters for years, kind and outcome.
- Kind
- Named in the records
- Records
- 79: 51 Board decisions, 28 facts from city reports
- Years
- 1956–2026
What the records say
The 60 most telling of its 79 records, in date order: the ones an editor picked first, then the highest scored. The one-line summaries were written by a language model from the printed page; open the page to check the wording.
| When | What the record says | Outcome | Source |
|---|---|---|---|
| 1956-06-18 | City approves an agreement with the Navy to treat sewage from the Hunters Point shipyard at the Southeast plant. | passed | Board decision scanned page ↗ |
| 1961 | The Southeast plant stands at Jerrold Avenue and Phelps Street. | other | Board decision scanned page ↗ |
| 1965-03-22 | Route approved for extending Southeast plant's outflow sewer | passed | Board decision scanned page ↗ |
| 1974 | Phase I San Francisco wastewater program · proposes: Secondary treatment at Southeast plant | project | City report: Tentative water quality control plan : San Francisco Bay Basin (2) : abstract scanned page ↗ |
| 1974 | Southeast plant · other: provides secondary treatment during the major portion of the year | site | City report: Draft environmental impact report and statement : San Francisco wastewater master plan scanned page ↗ |
| 1974 | Southeast Water Pollution Control Plant · proposes: secondary treatment of wastes | site | City report: Draft environmental impact report and statement : San Francisco wastewater master plan scanned page ↗ |
| 1974-03-10 | Public Works was asked to start sewage plant operations with supervisory staff, pumping sludge from North Point to Southeast Plant. | passed | Board decision scanned page ↗ |
| 1975 | S.F. Southeast Plant · cost usd: $100 million | project | City report: San Francisco Bay Region wastewater management facilities project coordination program report ... for BASSA, Bay Area Sewage Services Agency scanned page ↗ |
| 1975 | Southeast Plant · other: effluent to be relocated to ocean discharge after secondary treatment | recommendation | City report: San Francisco Bay Region wastewater management facilities project coordination program report ... for BASSA, Bay Area Sewage Services Agency scanned page ↗ |
| 1975-06-16 | Policy to build expanded sewage plant next to Southeast plant put off. | pending | Board decision scanned page ↗ |
| 1975-06-16 | Policy to build expanded sewage plant next to Southeast plant put off. | pending | Board decision scanned page ↗ |
| 1975-06-23 | Board adopted a policy to locate an expanded sewage treatment plant next to the Southeast plant. | passed | Board decision scanned page ↗ |
| 1975-07-21 | Expanded sewage plant to go beside the existing Southeast plant | passed | Board decision scanned page ↗ |
| 1977-04-04 | Grant money for interim work at Southeast plant; outcome unclear. | unknown | Board decision scanned page ↗ |
| 1977-06-27 | City to explore uses beyond planned park at Southeast plant | passed | Board decision scanned page ↗ |
| 1980 | Southeast Plant secondary treatment · cost usd: $410 million in improvements | project | City report: Clean water reporter. June 1980 scanned page ↗ |
| 1980 | Southeast Plant · other: will handle sewage from the eastern half of the City; being expanded | project | City report: Clean water reporter. June 1980 scanned page ↗ |
| 1980 | Southeast Plant · other: maximum dry weather rate of 140 million gallons a day | project | City report: Clean water reporter. June 1980 scanned page ↗ |
| 1980 | Southeast Plant · other: excess of up to 460 million gallons per day could be diverted across the City through the Crosstown Transport | project | City report: Clean water reporter. June 1980 scanned page ↗ |
| 1980 | Southeast Plant · other: when expanded, secondary treatment will be provided, removing some 90 percent of pollutants | project | City report: Clean water reporter. June 1980 scanned page ↗ |
| 1980 | Southeast Community Center · other: being planned adjacent to the Southeast Plant site as a mitigation measure | project | City report: Clean water reporter. June 1980 scanned page ↗ |
| 1980 | San Francisco North Point discharge · other: Transfer of North Point discharge to Southeast Plant site, a bit south of Bay Bridge, raises South Bay concentrations between Bay Bridge and Dumbarton Bridge | finding | City report: San Francisco Bay Region wastewater management facilities project coordination program report ... for BASSA, Bay Area Sewage Services Agency scanned page ↗ |
| 1982-07-12 | Resolution 537-82 lets Public Works hire a contractor for emergency electrical and mechanical repairs at Channel Pump Station and Southeast plant. | passed | Board decision scanned page ↗ |
| 1991-12-09 | Proposed $4,491,000 (≈ $11.1 million in 2026 dollars) appropriation for Public Works' Islais Pump Station and Southeast Plant design; sent to Finance Committee. | referred | Board decision scanned page ↗ |
| 1992 | Southeast Plant · owned by city: Department of Public Works, Bureau of Water Pollution Control | property_record | City report: How to do business with the city and county of San Francisco scanned page ↗ |
| 1992 | Bureau of Water Pollution Control, Southeast Plant · owned by city: Bureau of Water Pollution Control | property_record | City report: How to do business with the city and county of San Francisco scanned page ↗ |
| 1992-01-21 | The Board passed on first reading an ordinance appropriating $4,750,000 (≈ $11.4 million in 2026 dollars) for Islais Pump Station and Southeast Plant design. | passed first reading | Board decision scanned page ↗ |
| 1992-01-27 | Public Works was appropriated $4,750,000 (≈ $11.4 million in 2026 dollars) for Islais Pump Station and Southeast Plant design, with $250,000 (≈ $600,392 in 2026 dollars) placed on reserve; finally passed. | passed | Board decision scanned page ↗ |
| 1996 | Southeast Water Pollution Control Plant service area · finding: no capacity constraints that would restrict future development | finding | City report: Draft EIR : long range development plan, University of California, San Francisco scanned page ↗ |
| 1996 | UCSF LRDP wastewater generation · other: Wastewater generation approximately 0.525 mgd average dry weather flow, an increase of 0.9 percent over current Southeast Plant flows | finding | City report: Draft EIR : long range development plan, University of California, San Francisco scanned page ↗ |
| 1996 | Southeast Plant · other: LRDP wastewater would use about two percent of the Plant's current surplus capacity | finding | City report: Draft EIR : long range development plan, University of California, San Francisco scanned page ↗ |
| 1998-01-12 | Proposed $3,500,000 (≈ $7.2 million in 2026 dollars) for Southeast Plant sewage treatment construction was referred to the Finance Committee. | referred | Board decision scanned page ↗ |
| 1998-02-02 | Controller's $3.4M (≈ $7.0 million in 2026 dollars) appropriation for Southeast Plant aeration basin and pump station work passed for second reading. | passed first reading | Board decision scanned page ↗ |
| 1998-02-09 | Appropriates $3,468,646 (≈ $7.2 million in 2026 dollars) from the Clean Water fund for Southeast Plant aeration basins and a pump station upgrade. | passed | Board decision scanned page ↗ |
| 1999-12-01 | $250,000 (≈ $505,612 in 2026 dollars) sought for land to expand the Southeast plant pump station | resolution | Board decision scanned page ↗ |
| 1999-12-01 | $250,000 (≈ $505,612 in 2026 dollars) sought for land to expand the Southeast plant pump station | resolution | Board decision scanned page ↗ |
| 2000 | Public Utilities Commission Technical Review Committee · finding: if a plant is creating odors then it is not effectively working and is overloaded | finding | City report: Final environmental impact statement for the disposal and reuse of Hunters Point Shipyard scanned page ↗ |
| 2000 | Southeast plant · other: over 80% of all City discharges enter the plant | site | City report: Final environmental impact statement for the disposal and reuse of Hunters Point Shipyard scanned page ↗ |
| 2002-09-30 | Public Utilities Commission's $441,000 (≈ $825,962 in 2026 dollars) emergency contract for pump drives at the Southeast plant was sent to Finance Committee. | referred | Board decision scanned page ↗ |
| 2004 | Public Utilities Commission's $1.8 million (≈ $3.2 million in 2026 dollars) design-build contract with [name withheld] for a solar plant at the Southeast plant was proposed. | resolution | Board decision scanned page ↗ |
| 2004-02-04 | $5 million (≈ $8.9 million in 2026 dollars) sought for Southeast plant odor control | ordinance | Board decision scanned page ↗ |
| 2004-09-14 | The Public Utilities Commission may accept a state loan of about $1,622,940 (≈ $2.9 million in 2026 dollars) for solar and energy upgrades at the Southeast plant. | referred | Board decision scanned page ↗ |
| 2004-09-28 | Public Utilities Commission may accept a $1.6M (≈ $2.9 million in 2026 dollars) state loan for efficiency and solar work at the Southeast plant. | passed | Board decision scanned page ↗ |
| 2013-05-21 | Public Utilities Commission emergency contract of up to $9M (≈ $13.0 million in 2026 dollars) to replace unstable roofs at the Southeast plant at 750 Phelps Street was sent to committee. | referred | Board decision scanned page ↗ |
| 2013-07-16 | The Public Utilities Commission may sign an agreement of up to $80M (≈ $115.7 million in 2026 dollars) with Brown and Caldwell for [name withheld] sewer engineering. | passed | Board decision scanned page ↗ |
| 2013-07-16 | Up to $80 million (≈ $115.7 million in 2026 dollars) for consultants on sewage plant upgrade approved. | passed | Board decision scanned page ↗ |
| 2013-07-16 | Up to $80 million (≈ $115.7 million in 2026 dollars) for consultants on sewage plant upgrade approved | passed | Board decision scanned page ↗ |
| 2013-07-16 | Up to $80 million (≈ $115.7 million in 2026 dollars) for Southeast sewage plant digester design approved | passed | Board decision scanned page ↗ |
| 2014-06-03 | Public Utilities Commission seeks retroactive approval of an emergency contract, up to $225,000 (≈ $325,431 in 2026 dollars), to repair gas monitoring at the Southeast plant; sent to committee. | referred | Board decision scanned page ↗ |
| 2016-12-06 | Southeast plant design contract raised to $33.5 million (≈ $47.0 million in 2026 dollars), approved | passed | Board decision scanned page ↗ |
| 2017-05-09 | Sewage digester design contract raised $73.5 million (≈ $101.0 million in 2026 dollars), approved | passed | Board decision scanned page ↗ |
| 2019-12-17 | $5.5M (≈ $7.2 million in 2026 dollars) emergency repair to sewage pipe at Southeast plant approved | passed | Board decision scanned page ↗ |
| 2022-09-27 | Southeast sewage plant design services up to $208.5M (≈ $240.1 million in 2026 dollars) approved | passed | Board decision scanned page ↗ |
| 2024-07-16 | Southeast sewage plant design contract amendment approved | passed | Board decision scanned page ↗ |
| 1974 | Southeast plant bayside outfall (San Francisco municipal wastewater) · proposes: Bayside outfall abandoned; secondary effluent from Southeast and Richmond-Sunset plants pumped to Lake Merced for ocean outfall | project | City report: Tentative water quality control plan : San Francisco Bay Basin (2) : abstract scanned page ↗ |
| 1975 | San Francisco projects completed after 1980 · other: secondary treatment at Southeast Plant, finally ocean discharge | project | City report: San Francisco Bay Region wastewater management facilities project coordination program report ... for BASSA, Bay Area Sewage Services Agency scanned page ↗ |
| 1975 | Southeast Plant · proposes: secondary treatment at the Southeast Plant, then ocean discharge | building | City report: San Francisco Bay Region wastewater management facilities project coordination program report ... for BASSA, Bay Area Sewage Services Agency scanned page ↗ |
| 1975 | Interim Bay Outfall, Southeast Plant Expansion · lead agency: Department of Public Works | project | City report: Grants report : How much of what is in the second city budget scanned page ↗ |
| 1975 | Interim Bay Outfall, Southeast Plant Expansion · cost usd: 750,000 | project | City report: Grants report : How much of what is in the second city budget scanned page ↗ |
| 1975 | San Francisco Southeast Plant · other: large plant with significant water quality impact, bid scheduled winter 1977-8 in a cluster with South Bay Interceptor | project | City report: San Francisco Bay Region wastewater management facilities project coordination program report ... for BASSA, Bay Area Sewage Services Agency scanned page ↗ |
All 79 records, with filters · this place's data as JSON · release v0.7.1 · CC0 1.0